Site visit details

Overview

Catchment Dandenong
Site Hazel Vale Creek, 600 m upstream of Monbulk Creek ME_DHV010
Date and Time Friday 26th July 2013 11:00am
Approved Approved

Notes

Physical Chemical Tests

D.O. % D.O mg/L EC µS/cm pH pH Units rP mg/L P Air ° C Water ° C Turb NTU
Sample 95 10.7 800 0.06194 10 10 10
Weather overcast
Last rainfall During the last 24 hours 0.5
Flow estimate MEDIUM: flow is normal/typical average flow
Water Appearance Stained brown
Stream depth 51cm - 99cm
Stream width 2m - 5m
Hazards
Litter/Pollutants cans,packets,paper,plastic
unable to test pH as meter not working properly

Diary photos

No diary entries recorded for this visit