Waterwatch Data Portal
ME_YYD809 Chelsworth Overflow (stormwater capture draining to Reedy Billabong)
20 March 2015
Site visit details
Overview
Catchment | Yarra River |
---|---|
Site | Chelsworth Overflow (stormwater capture draining to Reedy Billabong) ME_YYD809 |
Date and Time | Friday 20th March 2015 09:20am |
Approved | Approved |
Physical Chemical Tests
Ammon-Nit mg/L NH3-N | D.O. % | D.O mg/L | EC µS/cm | pH pH Units | rP mg/L P | Air ° C | Water ° C | Turb FTU | Turb NTU | |
---|---|---|---|---|---|---|---|---|---|---|
Sample | 0.19 | 6.6 | 290 | 7.1 | 0.11 | 19 | 17 | 9 |
Weather | sunny |
---|---|
Last rainfall | During the last week 2 |
Flow estimate | STAGNANT: No continuous flow in channel but channel continuous (in-stream habitats connected) |
Water Appearance | Clear |
Stream depth | 0.2 |
Stream width | 1 |
Hazards | |
Litter/Pollutants |
No obvious flow from pipe but continuous stream of water from pipe to the billabong.
All content, files, data and images provided by the Waterwatch Data Portal and Gallery are subject to a Creative Commons Attribution License
Content is made available to be used in any way, and should always attribute Waterwatch and www.vic.waterwatch.org.au