Waterwatch Data Portal
GB_WCP003 Cussen Park Site 3 - Weir Wall, downstream
2 February 2015
Site visit details
Overview
Catchment | Goulburn River |
---|---|
Site | Cussen Park Site 3 - Weir Wall, downstream GB_WCP003 |
Date and Time | Monday 2nd February 2015 10:30am |
Approved | Approved |
Physical Chemical Tests
Chem mg/L | D.O. % | D.O mg/L | E coli orgs/100mL | EC µS/cm | Nitrate-Nit mg/L N | pH pH Units | Rain mm | rP mg/L P | Air ° C | Water ° C | Coli orgs/100mL | P mg/L | Turb NTU | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Sample | 58 | 5.2 | 230 | 6.9 | 0.92 | 21.6 | 33 |
Weather | sunny |
---|---|
Last rainfall | More than a week ago |
Flow estimate | PERMANENT: wetlands and lakes |
Water Appearance | |
Stream depth | |
Stream width | |
Hazards | |
Litter/Pollutants |
sunny day water level medium cormorant at site