Site visit details

Overview

Catchment Dandenong
Site Hazel Vale Creek, 10 m upstream of Monbulk Creek ME_DHV090
Date and Time Friday 26th July 2013 12:10pm
Approved Approved

Notes

Physical Chemical Tests

D.O. % D.O mg/L EC µS/cm pH pH Units rP mg/L P Air ° C Water ° C Turb NTU
Sample 81 9.4 710 0.03912 11 9 10
Weather sunny
Last rainfall During the last 24 hours 0.5
Flow estimate MEDIUM: flow is normal/typical average flow
Water Appearance Clear
Stream depth 51cm - 99cm
Stream width 2m - 5m
Hazards
Litter/Pollutants packets,paper,plastic
unable to test pH as meter not working properly

Diary photos

No diary entries recorded for this visit

Creative Commons CC BY
All content, files, data and images provided by the Waterwatch Data Portal and Gallery are subject to a Creative Commons Attribution License

Content is made available to be used in any way, and should always attribute Waterwatch and www.vic.waterwatch.org.au