Waterwatch Data Portal
GB_WCP003 Cussen Park Site 3 - Weir Wall, downstream
12 January 2015
Site visit details
Overview
Catchment | Goulburn River |
---|---|
Site | Cussen Park Site 3 - Weir Wall, downstream GB_WCP003 |
Date and Time | Monday 12th January 2015 12:10pm |
Approved | Approved |
Physical Chemical Tests
Chem mg/L | D.O. % | D.O mg/L | E coli orgs/100mL | EC µS/cm | Nitrate-Nit mg/L N | pH pH Units | Rain mm | rP mg/L P | Air ° C | Water ° C | Coli orgs/100mL | P mg/L | Turb NTU | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Sample | 42 | 3.3 | 154 | 6.5 | 0.92 | 27.7 | 6 |
Weather | sunny |
---|---|
Last rainfall | During the last 24 hours 10 |
Flow estimate | PERMANENT: wetlands and lakes |
Water Appearance | |
Stream depth | |
Stream width | |
Hazards | |
Litter/Pollutants |
sunny day water level high lots of water birds 10.0 mm rain overnight
All content, files, data and images provided by the Waterwatch Data Portal and Gallery are subject to a Creative Commons Attribution License
Content is made available to be used in any way, and should always attribute Waterwatch and www.vic.waterwatch.org.au